Tuesday, December 16, 2008

Circle G Ranch Project Update

Until today, we were ahead of schedule on the addition project in Circle G Ranch in Tempe. With the rain scheduled for the next three days, we will have to postpone further work until next week. We will install windows & skylights next week and the roof will get dried in. Framing on the existing house to tie into the new structure will commence once the house is dried in. As you can see from the progress photos, we didn't waste anytime to get the new structure framed.

New Front Elevation, inclusive of four car garage, entry tower, office and two bedrooms


Tie-in of existing roof line with new bedroom

New four car garage

Original entry to be removed

New entry tower