GW Custom Homes recently completed a small project for a client in North Cave Creek (actually just North of Cave Creek in the County - not too far from the new Gold Mountain Estates subdivision on Continental Mountain).
The scope of this project entailed constructing a new patio Ramada ,which included fabrication of a bridge across the pool spillway. Although this may sound pretty straightforward, the project site on the side of the mountain created some unique challenges.
Building permits were issued back in February of this year, work on the project was started in March and was completed in July. Site work, retaining walls and steel fabrication extended this project beyond the length of what one might expect this project to require. All in all, no time was wasted. The project came in on budget.
I would like to thank Ken Bartels , the Architect on the project and the home owner for providing us the opportunity to build the project.
The scope of this project entailed constructing a new patio Ramada ,which included fabrication of a bridge across the pool spillway. Although this may sound pretty straightforward, the project site on the side of the mountain created some unique challenges.
Building permits were issued back in February of this year, work on the project was started in March and was completed in July. Site work, retaining walls and steel fabrication extended this project beyond the length of what one might expect this project to require. All in all, no time was wasted. The project came in on budget.
I would like to thank Ken Bartels , the Architect on the project and the home owner for providing us the opportunity to build the project.
Photos of the project are posted below:
Presite - Existing Pool
Presite - Existing Pool Equipment
Retaining Wall Footing Excavation
Bridge Footer Excavation
Retaining Wall Footer
Bridge Footer
Retaining Walls & Waterproofing
Backfill & Pad
Bridge Steel
Bridge Concrete
Masonry Walls / Columns
Bridge Flagstone
Beams & Truss Installation
Roof Framing
Hood Framing / Electrical Rough
Boulders Install
Finished Bridge
Finished Ramada
Finished Appliances